LEGAL NOTICE
--------
Mt Washington Source Control Implementation
PROJECT ID NO. 10172940
This bid is designated as an electronic bid per CMC 321-24. The bid will NOT be read publicly. No hard copies of bids will be accepted. Bidders must submit bids electronically through the City’s Vendor Self Service website. Bidders must be registered to submit a bid. Bidders can register, find instructions and submit bids at:
https://vss.cincinnati-oh.gov/vssprod/Advantage4  
UNTIL 12:00 PM on Thursday,
March 30, 2023
at which time said bids will be compiled, reviewed and then later posted at https://www.cincinnati-oh.gov/noncms/cmgr/business-opportunities/  
Bidders may download Bid Documents from the Open Data Cincinnati website and should frequently return to the site to monitor for project-specific updates and addenda. https://www.cincinnati-oh.gov/noncms/cmgr/business-opportunities/
Questions on this project or any part of the Contract Documents and other project documents must be sent via e-mail to [email protected] by the established deadline. The deadline for questions is 12:00 PM local time on Thursday, March 23, 2023.
This project consists of the installation of approximately 6,100 LF of new storm sewer. The new sewer will vary in size from 12” to 54” in diameter and will require approximately 19 new manholes, and 31 new catch basins. Approximately 2630 LF of new 6” and 8” Ductile Iron water pipe and 25 water service reconnections are also included in the project.
The work takes place in City of Cincinnati’s Mt. Washington neighborhood, Ohio.
If a contract is awarded, it will be done so in accordance with the Contract Documents, including the method of award identified in Section H of the Instructions to Bidders in Section 00 21 13. The City reserves the right to reject any or all bids, to waive technicalities, or to advertise for new bids, if the best interests of the City will be promoted thereby.
The estimated cost of the Greater Cincinnati Water Works portion for this project is: $726,475.00. The estimated cost of the Metropolitan Sewer District of Greater Cincinnati’s portion for this project is: $7,285,000.00.
The established SBE Participation Goal for this project is: 10%.
Cincinnati, Ohio. March 9, 2023.
 
 
 
 